Blue Line trains heading east to the Van Aken District stop beside a small 1922 building at 18900 Van Aken Boulevard. Riders wait in the passenger shelter outside it. The building has been empty for about ten years. Its last tenants, going back over the century, were a tobacco shop and newsstand, a soda and candy shop, and a day spa. Farther west, just east of Shaker Square, Coventry Station at 14100 Shaker Boulevard sits beside the Green Line and has also been vacant for more than a decade.
On Oct. 7, the City of Shaker Heights listed both buildings for sale or long-term lease. It is the first time either one has been offered for sale. The listing arrived in the same autumn that GCRTA is spending heavily on Shaker's rail lines: new platforms, a new terminus station and a new fleet of trains. None of that money reaches these two buildings. Their future now depends on whether a private business wants to move in.
What the City Put on the Market
The city's notice calls these the only historic rapid transit stations left in Greater Cleveland, apart from the Terminal Tower/Tower City station. Both are protected historic properties, and both have been leased to private businesses for most of their lives.
| Coventry Station | Lynnfield Station | |
|---|---|---|
| Address | 14100 Shaker Blvd. | 18900 Van Aken Blvd. |
| Line | Green Line | Blue Line |
| Built | Early 1920s, by Standard Oil Company of Ohio | 1922 |
| Historic status | Inside the Shaker Square Local Historic District | Local Landmark; part of the Shaker Village National Register Historic District |
| Past tenants | Standard Oil, a floral shop, an insurance agency | Tobacco shop and newsstand, soda and candy shop, day spa |
| Vacant | About 10 years | About 10 years |
Lynnfield has its own place in the line's history. When it was built, it was the last stop on the rapid. The line was later extended to Warrensville Center Road. That end of the line is now where most of the new Blue Line spending is going.
The Transit Money Stops at the Platform Edge
GCRTA is rebuilding nearly every rail stop in Shaker Heights. In 2024 it received a $16 million federal grant for the Blue Line stations along Van Aken Boulevard. In September 2026, NEOtrans reported a $20 million Federal Transit Administration award. GCRTA is adding $5 million of its own, for a $25 million rebuild of eight Green Line stations in the Shaker Boulevard median.
The eight Green Line stations on the list are:
- Coventry
- Southington-Shaker
- South Park
- Attleboro
- Torrington
- Courtland
- Belvoir
- West Green
The work replaces 45-year-old platforms with new concrete ones. It adds tactile warning panels along the track edge, redesigned ramps and new sidewalks, plus a raised "mini-high" platform section for boarding. When it is done, GCRTA says every station in its system will be accessible under the ADA. Lee-Shaker, Warrensville-Shaker and Green Road already are. Lee-Shaker shows what the finished stops will look like. It was rebuilt in 2017 for $1.7 million with new platforms, ramps, shelters, lighting and landscaping.
Coventry is on that list. Riders there will get a new platform, while the 1920s building next to it gets nothing. According to the city, the station buildings "do not have a viable transit use nor do they fit into modern transit system needs," and their repair has not been part of any current or long-term capital plan. NEOtrans put it this way: GCRTA's investments in Shaker's stations "do not include these historic structures although they will have updated surroundings."
Courtland Shows the Other Outcome
There used to be three historic station buildings. The third stood at Courtland and Shaker Boulevard. It was built in the 1920s, like the other two, and torn down in the late 1960s. Courtland is also one of the eight Green Line stops getting a new platform. When that work happens, Courtland will have a new platform and no building, the same as it has had for more than 50 years.
The city says it has tried other options first. It held talks with GCRTA, sought historic preservation funding and recently completed preservation architectural reviews of both buildings. Staff are still looking for grants. Offering the buildings for sale or lease adds a second route, running alongside that grant search. In the city's words:
"Ideally, the buildings can be preserved with a long-term goal to return the buildings to active use."
What a New Tenant Could Open
The city is offering the buildings on the condition that they be rehabilitated and returned to commercial use. Both need significant rehabilitation. NEOtrans reported that zoning at both sites does not allow residential or live-work use. According to NEOtrans, the listing describes them as suited to boutique retail, a café, office, studio or another neighborhood-serving business. Both sit in walkable areas with many apartment buildings nearby and free parking next door.
The asking price has not been made public. The listing broker, Cushman & Wakefield | CRESCO Real Estate of Independence, referred media questions to city officials. The city's notice gives the broker contact for interested buyers and investors. Crain's Cleveland Business covered the listing on Oct. 23.
This post covers the listing as news. It is not guidance on zoning or historic district rules. Anyone thinking about these buildings should confirm the details with the city and their own attorney or advisors.
The Neighbors Arriving at the End of the Blue Line
Lynnfield sits just west of the Van Aken District, where the Blue Line ends. NEOtrans reported in September that GCRTA is building a new Van Aken-Warrensville station at that terminus. The nearly $18 million rail and bus facility will have public restrooms, a heated indoor waiting area and a platform that is mostly high-level, redesigned to fit the new railcars. HWH Architects Engineers Planners of Cleveland designed it, and Mike Coats Construction Co. of Niles is the general contractor. GCRTA's project page estimates construction will finish in fall 2026. It does not list an opening day.
According to the same NEOtrans report, Metropolitan Holdings is building Arcadia a block away, at 3393 Warrensville Center Road. The $62 million, five-story building will have 141 apartments and 15,000 square feet of ground-floor retail. RDL Architects plans to move its offices to the second floor. Paris Baguette has signed for one of the storefronts and is expected to open in late 2027. Two city-owned sites near the Blue Line have also won federal grants to study transit-oriented development. One is a 2-acre lot just east of the Van Aken-Warrensville station. The other is the Stephanie Tubbs Jones Community Building near the Van Aken-Lee stop.
On the Green Line end, Coventry sits just east of Shaker Square. The square's Vision Plan, as NEOtrans reported in August, was approved by the Cleveland City Planning Commission and proposes a better promenade, more space for pedestrians and possibly new housing nearby. It is still a plan, and nothing has been built.
Lee Road is also being rebuilt, which affects everyone driving between the two lines this season. Under the city's Lee Road Complete Street project, Phase 1 utility work south of Van Aken was scheduled to run through year-end. Lee Road is down to one lane each way between Van Aken and Lomond through November, with another lane restriction between Lomond and Invermere in November and December. The finished street will have a two-way off-road bikeway south of Van Aken, new sidewalks and 182 replacement trees. The city expects the whole project to be done in 2029.
Dates on the Line Through 2028
The trains are changing too. The first of GCRTA's new railcars, car No. 401, arrived at Cleveland's port on Aug. 31. GCRTA has ordered all 54 cars. Here is the schedule for the lines through Shaker:
- Oct. 7 to 12, 2026: #67R and #68R buses replaced Blue and Green trains between Tower City and both ends of the lines, running every 30 minutes. Train service returned Oct. 13.
- Fall 2026: GCRTA's estimated construction completion for the new Van Aken-Warrensville station.
- November and December 2026: Lee Road lane restrictions continue between Van Aken, Lomond and Invermere.
- Not yet scheduled: The $25 million rebuild of the eight Green Line stations, including Coventry. No construction dates have been published.
- August 2027: New railcars scheduled to start service on the Red Line.
- Late 2027: Paris Baguette expected to open at Arcadia.
- August 2028: New railcars scheduled to start service on the Blue and Green lines.
By August 2028, if the schedule holds, Blue and Green line riders will board new trains from new platforms. The one open question is whether Coventry and Lynnfield will have tenants by then.
For more than 35 years, Smith Garofoli Group has followed how changes to Shaker's streets, transit and historic buildings affect the homes nearby. If you live near the Blue or Green line and want to talk through how the station rebuilds and the Lee Road work might affect your plans, contact us. We're happy to talk it over.